nist-dev-infra was retired 2026-10-28. The next compliant hub should be built
on new nodes from the runbook, with etcd encryption from install. Neither runbook has been run end to end.

Completion criteria

NEW-HUB-RUNBOOK.md,
nist-dev-infra/RUNBOOK.md. Related: #673, #675.

Activity

  1. self-assigned this
    on Nov 17, 2026
  2. changed the title [-]Rebuild the compliant hub from the runbook[/-] [+]Build compliant-dev-infra, the compliant hub, on the R440s[/+] on Nov 17, 2026
  3. EldritchJS commented on Nov 17, 2026

    @EldritchJS
    Author

    Update (2026-11-17), agreed with tzumainn: the hub will be compliant-dev-infra, a new hub on the R440s built from nist-dev-infra's configuration, in the standard layout oac-dev-infra uses with oac-dev-workload1 and workload2.

    Runbook: compliant-dev-infra/RUNBOOK.md. nist-dev-infra's documents stay as the record of the first build. Plan and hardware: RHADS-PLAN.md option B2.

    Still to confirm: that six of the eight R440s are free (oac-infra lists them as future oac-prod-infra computes), that they are on the cluster and storage networks, the base domain (proposed: keep nist.int.massopen.cloud), and the workload cluster's name.

  4. EldritchJS commented on Nov 17, 2026

    @EldritchJS
    Author

    Correction to the layout above: no R440s as compute. The hub is three R440s as control plane and jetty's three FC430s as workers (they are freed when jetty is taken apart). Only three R440s are needed.

    Taking the FC430s ends jetty, and andalusia as built today, before the hub is installed. The runbook and plan are updated.

  5. EldritchJS commented on Nov 17, 2026

    @EldritchJS
    Author

    Update, 2026-11-17. Decided since the last comment:

    Built in phases, so jetty and andalusia keep running as long as possible:

    Phase What jetty / andalusia
    A Hub on the 3 R440s alone (compact for now): install, storage, compliance stages, scans Untouched
    B Remove andalusia from oac-dev-infra, then detach and power off jetty Down. Date to be agreed first
    C FC430s join as workers (oc adm node-image); masters stop taking workloads
    D compliant-dev-workload0 on jetty's GPU nodes (#787), then andalusia on it (#788) Rebuilt

    Phase A can start once the three R440s are named and on the cluster network. Runbook: https://github.com/EldritchJS/oac-eldritch-things/blob/main/compliance/compliant-dev-infra/RUNBOOK.md (section 2, "Phases").

  6. EldritchJS commented on Nov 17, 2026

    @EldritchJS
    Author

    Simpler order than the phases above: jetty and andalusia are only used by this work, so they come down first, and the hub is installed once with all six nodes (3 R440 control plane + 3 FC430 workers). No compact stretch, no adding workers afterwards.

    1. Remove andalusia from oac-dev-infra, detach jetty, power off and wipe its nodes
    2. Install compliant-dev-infra, 3+3, and harden it
    3. compliant-dev-workload0 on jetty's GPU nodes (GPU hypervisor cluster for compliant-dev-infra on the SD665 GPU nodes #787), then andalusia on it (Rebuild andalusia on compliant-dev-infra #788)

    No GPU VM cluster between step 1 and the end of step 3.

  7. EldritchJS commented on Nov 17, 2026

    @EldritchJS
    Author

    Correction: jetty's FC430s go back to the pool and are not this hub's workers. The hub is 3 R440s (MOC-R440-U14 to U16) as control plane plus 3 workers still to be assigned. jetty and andalusia come down once the hub's ISO is made (jetty is the FIPS node it is built on) and before #787.

  8. tzumainn commented on Nov 17, 2026

    @tzumainn

    It'd be easiest if we used new fc430 nodes rather than the one in jetty, since jetty nodes are configured through ESI right now. So I'd suggest:

    • R440s (I made up names, since I was just given their BMC addresses)
      • MOC-R440-U14 / 10.3.10.114
      • MOC-R440-U15 / 10.3.10.115
      • MOC-R440-U16 / 10.3.10.116
    • FC430s
      • MOC-R4PAC10U31-S1D / 10.2.13.164
      • MOC-R4PAC10U31-S3A / 10.2.13.165
      • MOC-R4PAC10U31-S3B / 10.2.13.166

    The R440s should already be on the cluster network; the FC430s still need to be configured!

  9. EldritchJS commented on Nov 18, 2026

    @EldritchJS
    Author

    Progress, 2026-11-18: the hub install started today.

    • Control plane: MOC-R440-U14 to U16. Workers: pool FC430s MOC-R4PAC10U31-S1D, -S3A and -S3B (S1D was switched from UEFI to BIOS mode to match the others; U15 and U16 needed Secure Boot turned off; thanks @tzumainn).
    • OpenShift 4.22.22, FIPS on. The ISO was built on one of jetty's FIPS nodes.
    • Root disks are encrypted with Tang (NBDE) against naved's Tang server, so the disk encryption box can be ticked once the install is verified (Determine whether to use NBDE for data-at-rest encryption in MOC 2.0 #672).

    Order change: jetty and andalusia now come down after the hub is installed and verified, not right after the ISO, in case the ISO has to be rebuilt (it was rebuilt once today, to add Tang).

  10. EldritchJS commented on Nov 18, 2026

    @EldritchJS
    Author

    The first install is up (control plane running, root disks unlocking through Tang). Once it finishes and checks out, the hub will be reinstalled, while it's still empty, from a new ISO that also encrypts the masters' etcd disks (CCI-MOC/oac-infra#36). jetty stays until that reinstall is verified.

  11. EldritchJS commented on Nov 18, 2026

    @EldritchJS
    Author

    The hub is installed (OpenShift 4.22.22, FIPS) on MOC-R440-U14 to U16 and the FC430s S1D, S3A and S3B, reinstalled from an ISO with every data disk Tang-encrypted: root disks, the masters' etcd disks and the workers' LVM Storage disks (CCI-MOC/oac-infra#36, #37, #38; #672, #811). FIPS and the Tang bindings were checked on every node; the kubeconfig is in Secrets Manager.

    jetty and andalusia are now being torn down: andalusia in CCI-MOC/oac-apps#252, then jetty in CCI-MOC/oac-apps#253, after which jetty's nodes are wiped and the SD665s move to #787. jetty's test volumes are already deleted.

  12. EldritchJS commented on Nov 19, 2026

    @EldritchJS
    Author

    jetty and andalusia are torn down: andalusia (CCI-MOC/oac-apps#252) and jetty (#253) removed from oac-dev-infra, their FlashBlade volumes deleted, jetty's nodes released and cleaned in ESI, its DNS (CCI-MOC/moc-dns#39) and AWS roles (CCI-MOC/moc-aws#81) removed, and the SD665s moved to compliant-dev-workload0's VLANs (CCI-MOC/ansible-switches#151) for #787.

  13. EldritchJS commented on Nov 19, 2026

    @EldritchJS
    Author

    Progress on the hub:

    Next: the ACS init bundle, then stage C (node hardening, every master reboots).

  14. EldritchJS commented on Nov 19, 2026

    @EldritchJS
    Author

    Progress, 2026-11-19:

    Next: scan and baseline, then verify.sh for the hub (#777), which now gates compliant-dev-workload0. The workload0 PR (restoring its hosted-clusters entry) goes up in parallel.

  15. EldritchJS commented on Nov 19, 2026

    @EldritchJS
    Author

    The hub passes verify.sh (#777): 73 PASS, 0 FAIL, with the known WARNs and scan gaps recorded. The two SD665-N V3s are wiped, approved and labelled for workload0 (#787). Next: merge CCI-MOC/oac-apps#260 and build compliant-dev-workload0 (runbook section 4).

  16. EldritchJS commented on Nov 20, 2026

    @EldritchJS
    Author

    compliant-dev-workload0 is built and hardened (#787): 4.22.22 with FIPS on the two SD665s, all four compliance stages applied. First verify: 19 PASS, 6 FAIL. The main open item is disk encryption on the SD665s (LUKS2 with Tang, needs a reinstall); the rest are verify.sh checks to adapt for hosted clusters, scan findings to go through, and Portworx. The FIPS build host (#792) is installed. Pausing for a few days; the runbook's section 4.6 lists where to pick up.

  17. joachimweyl commented on Nov 20, 2026

    @joachimweyl
    Contributor

    @EldritchJS, please add an estimate.

  18. EldritchJS commented on Nov 20, 2026

    @EldritchJS
    Author

    Estimate: about 2 days of work, once #736's PRs merge, to move the hub's compliance charts from the test branch to upstream and re-verify. #736 is mostly review time.

    Done so far: prerequisites, disk encryption (Tang/NBDE, #672), and the hub plus workload0 built and scanned. Hub verify.sh: 72 PASS, 0 FAIL. workload0: 32 PASS, 2 FAIL, both waiting on CCI-MOC/oac-apps#269.

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Metadata

Metadata

Assignees

Labels

NIST 800-171NIST 800-171 compliance relatedSTR: MOC 1.5 - Interim HW OpsIssues associated with Stream MOC 1.5 - Interim HW Ops

Type

No type

Projects

No projects

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions